May 07, 2024
WHAT?
The work serves to repair of the north and south embankments of the railway bridge by constructing a 20-meter concrete retaining wall on either sides of the track. The work to be performed will comply with Parks Canada’s Built Heritage requirements to preserve the locks over the Rideau Canal.
WHY?
To ensure safe and secure trains operations.
WHERE?
MP 1.2 Brockville Subdivision at Smiths Falls near the Rideau Canal (Old Slys Locks).
WHEN?
The work is planned to span from June 24 to December 31 2024.
The work will resume in 2025.