WHAT?
Installation and construction of culverts.
WHY?
To ensure safe and secure trains operations and improve hydraulic capacity of existing culverts.
WHERE?
-
8 locations on the Beachburg, Smiths Falls and Brockville Subdivisions in the Province of Ontario:
-
MP 4.15 Beachburg Subdivision
-
MP 16.50 Brockville Subdivision
-
MP 17.14 Brockville Subdivision
-
MP 21.60 Brockville Subdivision
-
MP 25.83 Brockville Subdivision
-
MP 7.61 Smiths Falls Subdivision
-
MP 20.61 Smiths Falls Subdivision
-
MP 28.77 Smiths Falls Subdivision
WHEN?
The work is planned to span from May 15th to November 15th 2025. Most of the work takes place at night. Work in a specific location can be expected to last a few days.