WHAT?
Installation and construction of culverts.
WHY?
To ensure safe and secure trains operations and improve hydraulic capacity of existing culverts.
WHERE?
15 locations on the Alexandria Subdivision in the Provinces of Quebec and Ontario:
-
MP 4.61 Alexandria Subdivision
-
MP 26.11 Alexandria Subdivision
-
MP 26.29 Alexandria Subdivision
-
MP 27.25 Alexandria Subdivision
-
MP 27.84 Alexandria Subdivision
-
MP 32.58 Alexandria Subdivision
-
MP 53.28 Alexandria Subdivision
-
MP 56.83 Alexandria Subdivision
-
MP 62.22 Alexandria Subdivision
-
MP 62.53 Alexandria Subdivision
-
MP 62.70 Alexandria Subdivision
-
MP 63.92 Alexandria Subdivision
-
MP 65.93 Alexandria Subdivision
-
MP 66.64 Alexandria Subdivision
-
MP 74.50 Alexandria Subdivision
WHEN?
The work is planned to span from June 15th to December 15th 2024. Most of the work takes place at night. Work in a specific location can be expected to last a few days.