WHAT
VIA will be replacing track components, performing track surfacing, rail destressing, rail milling as well as rehabilitating public grade crossings to improve track conditions.
WHY
For safety purposes and to comply with current federal regulation.
WHERE
On the Alexandria, Beachburg, Smiths Falls, Brockville and Chatham Subdivisions.
WHEN
April 15th to November 14th 2025. Most of the work takes place at night.
Specifically (dates are subject to change) :
-
Chatham Subdivision : April 15th to May 28rd
-
Alexandria Subdivision : July to August
-
Beachburg Subdivision : June
-
Smiths Falls Subdivision: September
-
Brockville Subdivision: May 13th to October 13th
The work to be performed is linear: work in a specific location can be expected to last a few days.
Works planned at Grade Crossings (detours to be expected during the evening/night):
-
Smiths Falls Sub. MP 3.26 – Transitway Road – September
-
Smiths Falls Sub MP 5.73 - Jockvale Road -– September